Step 1 - Place first panel into step beams at far left side of shelf. Position panel so required transverse flue space is maintained between left edge of panel and shelf in adjacent rack bay.
Step 2 - Tek screw 2 left hand corners of first panel into step beam.
Step 3 - Position remaining deck panels into step beam, overlapping as required at joints.
Step 4 - Tek screw remaining panels into beam through overlapping joints and at 2 right hand corners.