Punch Deck Installation Recommendations

Step 1 - Place first panel into step beams at far left side of shelf. Position panel so required transverse flue space is maintained between left edge of panel and shelf in adjacent rack bay.

Step 2 - Tek screw 2 left hand corners of first panel into step beam.

Step 3 - Position remaining deck panels into step beam, overlapping as required at joints.

Step 4 - Tek screw remaining panels into beam through overlapping joints and at 2 right hand corners.


DACS, Inc. recommends the following instruction for installation of Punch Deck. This installation procedure is based upon testing done by DACS, Inc., and is intended to provide the end user of the rack system the strongest, most durable system possible. All published rack deck load information is based upon these installation procedures. If these installation instructions are not folllowed, DACS, Inc. will not be held responsible for rack deck failures.

© 2020 DACS, INC. ALL RIGHTS RESERVED PUNCH DECK, FLUEKEEPER, THE PUNCH DECK LOGO AND THE FLUEKEEPER LOGO ARE REGISTERED TRADEMARKS OF DACS, INC.